Irem Spa

Yanshib

Companies: Irem Spa - Irem France

Client: Yanshib

Job description: YANSAB Olefins 1 Plant

Scope of work: Piping prefabrication and erection; Piping supports prefabrication (Subcontract) and erection; Steel structure erection; Mechanical erection; n.8 Furnaces erection; Piping Painting (Subcontract); Piping and Equipment Insulation (Subcontract); Scaffolding (Subcontract); Precommissioning; Reinstatement; Assistance to commissioning.

Mechanical works: Prefabrication and Erection of approximately 14.000 tons of piping, with approximately:
7.400.000 direct man-hours.
1.700.000 indirect man-hours
930.000 staff man-hours


Period carried out: December 2006 - October 2008

Location: YAMBU (SAUDI ARABIA)

Peak manpower: 2.500

Manhours: 7.400.000

Plan details: MAIN QUANTITIES: Piping Prefabrication & Erection: 14.000 Tons
Welding Inches: 1.036.000''
Steel Structures: 9.500 Tons
Mechanical Erection (Equipment Machinery & n. 8 Furnaces): 36.000 Tons

MAIN EQUIPMENT: more than 60 mobile cranes and mobile platforms, 1.100 welding sets, 60 power generators, compressors, plasma cutting machines, skylift, plus various items as trucks, motorcars etc

PREFABRICATION WORKSHOP FOR THE PROJECT
Total Covered area: 15.500 sqm
Covered area for Carbon steel and alloy steel prefabrication: 8.000 sqm
Covered area for Stainless steel prefabrication: 3.200 sqm
Laydown, drainage, handling and cargo area: 165.000 sqm