Companies: Irem Spa - Techimp Impianti Spa - Consorzio Italoffshore
Client: Eni
Job description: EPC Contract: Debottlenecking 2 Project
Scope of work: EPC : Civil , Steel Structures, Equipment and Machinery, Piping Erection, Insulation, Painting, E&I, Precommissioning and Commissioning.
Start date September 2013 - Completion date March 2016
Location: VAL D'AGRI (Italy)
Peak manpower: 800
Manhours: 2.600.000
Plan details: EPC: Engineering, Procurement, C onstruction (Civil , Steel Structures, Equipment and Machinery, Piping Erection, Insulation, Painting, E&I,) Precommissioning and Commissioning