Irem Spa

Nuon

Companies: Irem Spa - Techimp Impianti Spa - Irtis Srl

Client: Nuon

Job description: IGCC: Integrated Gasification Combined Cycle Power Plant 3 Power Units x 440MW

Scope of work: MECHANICAL, PIPING, STEEL STRUCTURES, SCAFFOLDING, PAINTING, INSULATION, E&I WORKS FOR No. 3 UNITS X 440 MW COMBINED CYCLE POWER PLANT-

Period carried out: January 2011 - March 2013

Location: Eemshaven (Netherlands)

Peak manpower: 500

Manhours: 1.000.000

Plan details: • Erection of 3 Gas Turbine
• Erection of 3 Steam Turbine HP/LP
• Erection of 3 Generators
• Around equipment piping erection
• Balance of plant piping erection
• Cooling water lines
• Prefabrication and hook-up of Pre-Assembled Racks (PARs)

Piping quantities: 2200 Tons

E&I quantities: Cables : 1.200 Km; Connections: 30.000