Irem Spa

Motor Oil Hellas

Companies: Irem Spa

Client: Motor Oil Hellas

Job description: Mechanical Erection of Hydrocracker and Hydrogen Unit

Scope of work: Piping quantities:
*piping fabrication :2.260 tons
* 237.000 welded inches
* piping erection 3.773 tons.

Start date May 2004; completion date September 2005.

Location: Aghii Theodori (Greece)

Peak manpower: 500

Manhours: 1.300.000

Plan details: Type:
* F7601 Steam Reformer Heater with 76 roof/burners. Total weight 1.440 tons. Supplier: KTI Italy
Work schedule: 6 months including precommissioning activities and catalyst loading.

Type:
* F7501 MCH Reactor Feed Heater with 12 floor/burners. Total weight: 375 tons.
* F7503 HDT Reactor Heater with 12 floor/burners. Total weight: 375 tons.
* F7502 HDT Atmospheric Distillation Heater with 14 floor/burners. Total weight: 675 tons.
Supplier: Kirchner Italia SpA.
Work schedule: 6 months including precommissioning activities and catalyst loading.