Irem Spa

ORASCOM Construction

Companies: Irem Spa

Client: ORASCOM Construction

Job description: Erection, testing, pre-commissioning, and assistance in commissioning of the entire mechanical, electrical, and instrumentation works for Module n°2 and Module n°3

Scope of work: Work Schedule: Start date June 2016 Completion date February 2018
Scope per each Module includes but not limited to:
• Two (2) gas turbines & generators
• One (1) steam turbine & generator
• One (1) condenser
• Two (2) heat recovery steam generators
• Two (2) exhaust by-pass stack
• Fin fan coolers
• Main and auxiliary transformers
• Generator circuit breakers
• Iso-phase bus ducts
• All systems, all associated auxiliaries, skids, pumps, hoists, containerized equipment and accessories, all interconnecting piping and cables; excluding only the erection of the wet cell cooling tower

Location: E

Peak manpower: Direct 1750 Ind 430

Manhours: Direct 5.300.000

Plan details: Main quantities:
- Piping & Supports erection 2.000 tons
- Piping erection 90.000 inch
- Steel Structure erection 6.794 tons
- Painting 23.600 sqm
- Insulation 50.000 sqm
- Equipment erection n°120/ 250 tons
- Erection of Turbines n°6/ 3000 tons (n°4 GT / n°2 ST)
- Erection of Generators n° 6/2100 tons
- Electrical Equipment Transformers n° 6/1140 tons
- Bus ducts 600 mt
- Cables 520 km