Projects

Client:
NUON / MHI
To be executed in Consortium with FABRICOM / FIP MAGNUM / PONTICELLI

Location:
EEMSHAVEN (THE NETHERLANDS)

Job description: 
MECHANICAL, PAR's Hook-up, PIPING, STEEL STRUCTURES, SCAFFOLDING, PAINTING, INSULATION, E&I WORKS,
3 UNITS X 440 MW COMBINED CYCLE POWER PLANT
Plan Details:
IGCC: Integrated Gasification Combined Cycle Power Plant
3 Power Units x 440 MW. Each line includes Vertical Boiler, Gas Turbine, Steam Turbine and Generator in single shaft configuration
  • Erection of 3 Gas Turbine
  • Erection of 3 Steam Turbine HP/LP
  • Erection of 3 Generators
  • Around equipment piping erection
  • Balance of plant piping erection
  • Cooling water lines
  • Prefabrication and hook-up of Pre-Assembled Racks (PARs)

 


Numbers: 
Direct Manhours 3.200.000; Manpower Peak 1.500; Staff personnel 250
 
Main Quantities:
  • Piping: 2200 tons
  • E&I quantitiesCables : 1.200 Km  -  Connections: 30.000

Date:
JANUARY 2011 - MARCH 2013

 