Client:
TOTAL / AMEC FOSTER WHEELER
Location:
ANTWERP (BELGIUM)
Job description:
PIPING, MECHANICAL, STEEL STRUCTURES, PAINTING, INSULATION, SCAFFOLDING WORKS, PREFABRICATION, INSTALLATION and HOOK-UP OF MODULES - ISBL& OSBL
Numbers:
Direct man-hours: 1.234.867 - Indirect man-hours 221.945; Manpower peak: direct manpower 470 units, indirect manpower 66 units
Construction Main Quantities:
-
STEEL STRUCTURES ERECTED – 1,089 Tons
-
PIPING ERECTION LARGE AND SMALL BOORE - 1,764 Tons
DIA-IN WELDED ON SITE – 66,462
DIA-IN WELDED IN PREFABRICATION - 89,326
-
STEAM TRACING INSTALLED – 43,6 Tons
-
STEAM TRACING STATIONS INSTALLED – 393 stations
-
EQUIPMENTS INSTALLED – 992 Tons
-
PIPERACK 2 – 9 PAR modules with:
235 Tons of steel structure
335 Tons of pipes
23 Tons of steam tracing
-
TIE - IN executed (cold and hot tap) - 285
Date:
OCTOBER 2014 - NOVEMBER 2016