Client: 
EEHC / ORASCOM CONSTRUCTION
Location:
BURULLUS (EGYPT)
Job description: 
PIPING, MECHANICAL, E&I, SCAFFOLDING, INSULATION, PAINTING WORKS FOR TWO POWER BLOCK MODULES N°2 AND N°3 
Numbers: 
Direct manhours 5.300.000 - Indirect manhours 2.400.000, Manpower Peak 1750
 
Main Quantities:
- 
Piping & Supports erection 2.000 tons
- 
Piping erection 90.000 inch
- 
Steel Structure erection 6.794 tons  
- 
 Painting 23.600 sqm
- 
 Insulation 50.000 sqm
- 
 Equipment erection n°120/ 250 tons
- 
 Erection of Turbines n°6/ 3000 tons (n°4 GT / n°2 ST)
- 
 Erection of Generators n° 6/2100 tons
- 
 Electrical Equipment Transformers  n° 6/1140 tons
- 
 Bus ducts 600 mt
- 
 Cables 520 km
Date:
JUNE 2016 - JUNE 2018