Client:
ITER / AIR LIQUIDE
Location:
CADARACHE (FRANCE)
Job description:
PIPING ERECTION, STRUCTURE ERECTION, SUPPORT ERECTION, ERECTION OF EQUIPMENT (GAS BAGS, PUMPS, COMPRESSORS, TANKS, VESSELS, SKIDS, HELIUM DRYER BY SKIDDING METHOD, COLD BOXES), PNEUMATIC TEST, PAINTING
Numbers:
Direct manhours 159.000
Date:
MARCH 2019 - JUNE 2021
Quantities:
Piping erection: 175 Tons/ 16.500 inch
Piping SS/CS (thk trom 1.6 to 9.53): 10.500" /6.000"
02 Lines (erection+Pref): 2.000"
Structure: 20 Tons
Painting: 2.150 mq
Equipment erection: n. 185 / 3100 Tons