Client: 
PREEMRAF AB / AMEC FOSTER WHEELER ENERGY LTD  

Location:
LYSEKIL (SWEDEN)

Job description: 
PIPING, MECHANICAL, STEEL STRUCTURES, FIREPROOFING, PAINTING WORKS

Numbers: 
Direct manhours: 800.000 Mechanical Works, 96.000 E&I Works - Indirect manhours 41.000 - Staff Manhours 137.000

 

Main Quantities (Mechanical Works):
  • Supply & Erection of 650tons of Steel Structures, including application of 4,431SQM of Fireproofing and application of 11.000sqm of galvanization;
  • Fabrication & Erection of 780Ton of piping, Including supply and erection of piping supports and application of 12.500sqm of painting
  • Erection of Equipment per 1.345tons, mainly pump and
  • Compressors including a Fire Heater & Vacuum Column;
  • Installation of 20.000mtl of steam tracing;

Date:
FEBRUARY 2017 - FEBRUARY 2019

 

Copyright © 2020 IREM S.p.A. All rights reserved.